Preparing your site for cabin delivery is mostly groundwork and planning. Whether you have ordered a security hut or kiosk or a portable cabin or site office, a Karmod unit is built in the factory and arrives as a finished building, so nothing is assembled on the day: it is lifted off the lorry and set down on its base.
Every unit needs a firm, level base, and we advise on the right one for your unit and site when we prepare your quote. The usual options are:
Whichever you choose, it should be level across the footprint, cured if concrete, and clear of standing water. On one of our projects, a MetroCity unit used as a site office was raised on a kerb to keep it clear of surface water. If the unit sits raised, plan the steps at the same time.
Ask a groundworker or structural engineer to size the base for the unit's weight and your ground.
| Range | Weight |
|---|---|
| Insulated panel cabin | 100 kg to 380 kg |
| GRP cabin | 280 kg to 650 kg |
| MetroCity modular cabin | 700 kg to 1,400 kg |
| KompoCity composite cabin | 850 kg to 1,900 kg |
| Bulletproof security cabin | 3,000 kg to 10,500 kg |
| Container layouts | Ask us for your layout and size |
Walk the route from the road to the pitch as if you were driving. Look for narrow gateways, tight bends, room to turn, height limits such as archways and branches, surfaces that may not take a loaded lorry, and parked cars or skips.
If the unit has to be lifted from the street, see our guide to portable cabins on tight city sites.
There are three usual ways to offload a unit:
Insulated panel, MetroCity, KompoCity and bulletproof cabins are placed with a forklift or crane. GRP cabins can be lifted on straps by a truck-mounted crane. The FlixBus ticket kiosk, for example, arrived as a finished unit and was lifted off the lorry by crane.
Before the day, check:
In Great Britain, the Lifting Operations and Lifting Equipment Regulations 1998 (LOLER) require employers to make sure every lifting operation is properly planned by a competent person, appropriately supervised and carried out safely. That plan relies on accurate information about your ground and anything overhead.
Settle where the unit sits and which way it faces before you order. We confirm the layout on a drawing before production, so check the door, window and fitting positions on it against your site.
Whatever electrics the unit has inside, connecting it to a supply is a separate job on site for a qualified electrician.
Before delivery, agree where the supply will come from: an existing building, a temporary site supply or a new connection (ask the network operator early). Agree the cable route too, and where it enters the unit, so ducts go in before the base is finished.
If the unit is a garden room or garden office fed from your home's supply in England, Part P of the Building Regulations applies and a new circuit is notifiable work. Use an electrician registered with a competent person scheme, who can self-certify it. If your electrician is not registered, speak to building control before work starts: the work usually has to be notified to them, though for some work a third-party certifier can be appointed instead. Wales, Scotland and Northern Ireland have their own rules, so check with your local building control.
In our welfare cabins and WC units and other layouts with a WC, the WC compartment is plumbed and fitted before the unit leaves the factory. Connecting water and waste to your site's services is work for a plumber or drainage contractor. Before delivery:
In England and Wales, the sewerage company for your area must be given notice before a drain is connected to a public sewer (section 106 of the Water Industry Act 1991). Contact it early; in some areas it is not your water supplier. Where there is no sewer, septic tanks, small treatment plants and cesspools have their own rules; in England these are set out in gov.uk guidance.
Website prices exclude VAT, delivery and offloading. Before sending your formal quote, we check the drawing, the delivery route to your postcode and the offload equipment. To help, send us:
Sending a request does not commit you to anything. Planning permission is a separate question, covered in our guide to portable cabins on private land.
| Check | Ready when | Who usually handles it |
|---|---|---|
| Base | Firm, level, cured if concrete, positioned to our base advice | Your groundworker |
| Route | Gates, bends, height limits and weak surfaces checked | You, then us before the formal quote |
| Lorry or crane position | Firm standing near the pitch, away from trenches, drains and cellars | You or your site manager |
| Overhead | Lift path clear of lines and branches; line owner consulted if lines are near | You; tell us what you find before the offload is planned |
| Swing space | Lift area clear of people, vehicles and materials | Your site manager |
| Offload equipment | HIAB, crane or forklift confirmed | Karmod, in the formal quote |
| Doors and windows | Positions agreed, room for steps | You, on our drawing |
| Power | Supply point, cable route and ducts ready; electrician booked | Your electrician |
| Water and drainage | Routes planned; sewerage company contacted about a sewer connection, or off-mains system planned | Your plumber or drainage contractor |
| Permissions | Planning position checked with the local planning authority | You |
| On the day | A named contact on site the driver can phone | You |
Choose a layout and size and send a request through our quote page, or contact us with any questions. You can also call 0116 403 0143, Monday to Friday, 8am to 6pm.






A soft or sloping pitch usually needs more groundwork to make it firm and level, and it can limit where a lorry or crane can stand. Have a groundworker look at it, and mention it when you ask for a price so our base advice takes it into account.
It can. Crane and HIAB lifts are usually stopped in high winds, and the person in charge of the lift makes that call on the day. Heavy rain can also soften the ground where the lorry or crane stands, so check that area again the day before.
Yes, ideally someone who knows the site and can make decisions. They can open gates, have parked cars and skips moved, show the driver the pitch and confirm which way the unit faces before it is set down, because changing it afterwards means another lift.
Treat it as a new delivery: a ready base at the new position, access for the lorry or crane and a clear lift area. Before the lift, have your electrician and plumber disconnect power, water and waste, and take away any loose steps or ramps.
Karmod container cabin prices by layout and size, what electrics, heating and fittings add, what the listed price leaves out, and how to get a firm quote.
The full welfare checklist for GB construction sites under CDM 2015: what each facility involves, who must provide it from day one, and the Karmod units that cover it.
Portable cabin, container office or modular building? What each term means, how Karmod's units are built, and which type suits a site, a gate or a garden.
Talk to our UK team
Tell us what the building is for and where it is going. We will suggest a unit, check delivery and send a formal quote.