Construction Site Set-Up Checklist: Offices, Welfare and Security Cabins

· 8 min read · Karmod International UK

A construction site set-up checklist should define the facilities your team needs, where each cabin will go, how people and deliveries will reach it, and who will prepare the ground and connect the services. Agree these details before dispatch so the cabins can be brought into use when the site needs them.

For a site manager buying portable cabins, the practical starting point is a coordinated plan for the office, welfare area and entrance. This guide helps you turn that plan into a cabin brief, a delivery programme and a clear division of responsibilities.

Construction site set-up checklist at a glance

StepWhat to establishRecord before moving on
1. Define the site briefPeak workforce, working pattern, office tasks and welfare needs.A facilities list for each project phase.
2. Choose the cabin layoutsRooms, fittings, entrances and usable space for the intended activities.The selected models, options and agreed drawings.
3. Draw the compound layoutCabin positions, pedestrian access, delivery routes and service points.A marked plan showing how the compound will operate.
4. Allocate responsibilitiesGround preparation, haulage, offloading and final utility connections.Named contacts and the agreed scope for each task.
5. Coordinate deliveryStock availability, destination, access and the readiness of the receiving area.A delivery arrangement confirmed for the project.
6. Prepare for occupationCompleted connections, functioning facilities and arrangements for ongoing use.A handover check with outstanding actions resolved.

Define what the site needs before choosing cabin sizes

Start with the busiest stage of the project. The office demand during initial groundworks may differ from the demand when several trades are working together. Record both, particularly if the compound will grow or move.

Your cabin brief should cover:

  • People: the maximum number on site at once, office staff, visitors and overlapping shifts.
  • Activities: desk work, meetings, inductions, breaks, changing and any task-related need for showers.
  • Equipment: desks, plan storage, kitchen appliances and other items that affect the layout or services.
  • Programme: the required opening date, project duration and any planned relocation.
  • Site conditions: available space, entrance restrictions, existing service points and photographs of the proposed location.

Use this brief when comparing portable site office solutions. Mark furniture and door movements on the proposed plan: the external footprint alone does not establish how many people can use a room comfortably or safely.

Match office and welfare layouts to the work

A combined office and WC may suit one set of requirements; another project may need separate office, eating and changing areas. Select the facilities first, then check which layouts can accommodate them.

Requirement to discussKarmod layout to considerCheck on the drawing or specification
An open office for desks and project administrationK1002 Open-Plan Portable CabinDesk positions, door location, circulation and selected electrical options.
Office space with a WC and kitchenetteK2004 Site Office with WC & KitchenetteThe working area remaining around the WC, kitchenette and entrance.
Two rooms with shared WC and kitchenette facilitiesK3003 Site Welfare UnitHow each room will be used, its furniture and the access through the separate entrances.
A welfare layout that includes a showerK3006 Welfare Unit with Shower Room & KitchenetteShower use, water heating, service requirements and the remaining room arrangements.

These layouts are starting points for selection. The number of units and facilities needs to follow your site's assessed requirements. Do not assign a workforce capacity from a product photograph or assume that one combined unit covers every welfare need.

For sites in Great Britain, HSE's construction welfare guidance explains that the facilities required depend on the workforce and the work undertaken. Our construction site welfare requirements guide covers this subject in more detail. Northern Ireland has its own CDM 2016 framework.

Plan the entrance, walking routes and service access together

Place the proposed cabins on a site drawing before finalising the order. Include the direction of each entrance door, the route from the site gate, the delivery approach and the position of utility connections.

Where a staffed entrance is needed, compare security gatehouses and access-control cabins against the actual tasks at the gate. Consider the operator's view, visitor sign-in and the location of any separately specified barrier controls or communications equipment.

HSE's site traffic guidance emphasises separating pedestrians and vehicles, planning suitable routes and reducing reversing. Apply that to the cabin arrangement: a convenient office position still needs a safe approach for the people using it.

Walk through three journeys on your drawing: a visitor reaching reception, a worker taking a break and a vehicle making a delivery. Mark any crossing or obstruction for the site team to resolve. Also consider how cleaners or maintenance contractors will reach the facilities once the compound is occupied.

Agree the supply and site-work responsibilities

Separate the cabin order from the tasks needed to receive and connect it. This gives the buyer, supplier and site contractors a shared record of what must happen before the facilities open.

ItemResponsibility or agreementWhat to confirm
Cabin model, layout and fittingsThe agreed Karmod order specification.The selected layout and options, including the factory-fitted services specified in the order.
Ground and base preparationThe customer.Have the proposed base and support arrangement checked against the selected cabin and site conditions before preparing it.
Transport to siteDepends on the agreement for the order.Who arranges haulage, the destination, access information and any delivery restrictions.
Offloading and positioningConfirm separately in the written delivery scope.The agreed method, equipment and responsible contractor; do not infer these from a transport price.
Final electricity, water and drainage connectionsThe customer, through appropriate site contractors.Connection requirements, contractor attendance and completion before the facilities are used.
Day-to-day operationThe site's management arrangements.Who will manage access, cleaning, consumables, maintenance and fault reporting.

For the practical information to send before delivery, use our cabin delivery preparation guide. Give the transport and offloading contractors the actual access conditions, including restricted turns, overhead obstructions and any limitations near the receiving area.

Build the delivery programme around site readiness

Karmod holds stock. If the required unit is available, delivery may be arranged sooner, depending on the destination and whether the receiving site is suitable and ready. Stock availability is one part of the programme; transport and site preparation still need to be coordinated.

Special projects, more complex configurations and orders involving multiple units have project-specific lead times. Confirm the programme against the actual specification and scope rather than applying a standard delivery promise to every order.

Work backwards from the date the facilities must be usable. Schedule the base preparation, transport, offloading and customer-arranged utility connections in that order, allowing the relevant contractors to confirm their availability. For a phased compound, identify which facilities must be operational first and which can follow later.

Complete a readiness check before the facilities open

Under HSE's guidance on principal contractor duties, suitable welfare must be available from the start of the construction phase and maintained throughout it. Treat the opening date as the point when facilities are functioning, rather than simply the date the cabins arrive.

Before bringing them into use, confirm that:

  • The supplied units and selected fittings match the agreed order.
  • The appointed contractors have completed the installation checks relevant to their work.
  • Customer-arranged final utility connections are complete and the connected equipment has been checked.
  • Entrances and the agreed pedestrian approaches are usable and clear.
  • Washing facilities have the water supply and consumables required for use, checked against HSE's toilets and washing guidance.
  • The site team has assigned cleaning, replenishment and fault-reporting responsibilities.

Keep the cabin drawings, order specification and relevant handover information with the site records. Revisit the layout if the workforce, work areas or delivery routes change during the project.

Questions about setting up a site compound

How many cabins does a construction site need?

The number depends on the facilities required, the people using them at the busiest time and the agreed internal layouts. Start with the office, welfare and entrance functions, then check the selected plans against the site's requirements. A cabin's external size alone is not a capacity rating.

Who prepares the ground and connects a Karmod cabin?

The customer is responsible for ground preparation and the final on-site utility connections. Confirm the selected unit's requirements and arrange the appropriate contractors before delivery. Factory-fitted items are determined by the agreed order specification.

Is transport and offloading included in the cabin order?

Transport arrangements depend on the agreement for the order. Offloading and positioning also need to be explicitly covered in the written scope, including who provides the necessary equipment and carries out the work.

How quickly can stock cabins be delivered?

An available stock unit may allow a shorter delivery programme, subject to the destination, transport arrangements and site suitability. Special, complex and multi-unit projects need a programme agreed for their specific scope.

Discuss your site cabin requirements

Send Karmod your site postcode, required opening date, peak workforce, facilities list and a marked plan or photographs of the proposed location. Include the available services and any delivery restrictions so the discussion can cover the cabins and the arrangements needed to receive them.

Request a site office and welfare cabin quotation to discuss suitable layouts, current stock and delivery arrangements for your project.


 

More guides

Talk to our UK team

Planning a site, a gatehouse or a garden office?

Tell us what the building is for and where it is going. We will suggest a unit, check delivery and send a formal quote.

Phone
0116 403 0143
Email
info@karmodint.co.uk
Opening hours
Mon - Fri, 8:00 AM - 6:00 PM GMT
Address
Unit 4 Fairfield Industrial Estate, Fair Farm Drive, Melton Road, Waltham On The Wolds, Melton Mowbray, LE14 4AJ
0116 403 0143
WhatsApp Us Instant modular support